Promises Made. Promises Delivered.
Long-term facility planning and an owner-focused approach helped Fern Ridge deliver every original bond commitment while creating additional value for students and the community.
Fern Ridge School District’s 2024 bond program is nearing completion approximately 10 months ahead of schedule and 15% below budget, with every commitment identified in the original bond measure addressed.
Approximately 98% of the physical work is complete, and the district projects approximately $3.15 million in remaining program contingency after planned transfers and closeout allowances. More than 90% of the design and construction firms engaged for the program are based in Lane County.
Those results represent more than two years of active construction across the district. The planning behind them began much earlier.
By the Numbers: Fern Ridge 2024 Bond Program
$16.115 million voter-approved bond
$6 million state OSCIM grant
$23.904 million current program budget
Approximately 98% of physical bond work complete
Approximately 10 months ahead of schedule
Approximately 15% below budget
Approximately $3.15 million in remaining program contingency after planned transfers and closeout allowances
More than 90% of design and construction partners based in Lane County
The Work Started Before the Bond Passed
Successful capital programs rarely begin with design or construction. They begin with understanding the owner’s facilities, priorities and long-term goals.
Before Fern Ridge asked voters to invest in its schools, the district completed detailed facility assessments and long-range facility planning. That work established a roadmap for existing conditions, educational priorities, project needs and potential sequencing.
When voters approved the bond, Fern Ridge did not have to begin again.
The knowledge developed during planning carried directly into implementation. As architects, engineers, contractors and other partners joined the program, they entered with a clearer understanding and leadership of what was included, what was not included and why those decisions had been made.
That continuity is central to R&C Management Group’s owner-focused approach. The district’s goals and priorities are established first, then design and construction teams are brought in to help deliver them.
More Than a Decade of Fern Ridge Knowledge
R&C Senior Project Manager Scott Rose’s relationship with Fern Ridge School District extends back more than a dozen years.
That history provided knowledge of the district’s buildings, previous improvements, infrastructure challenges, staff priorities and community needs before the current bond program began.
Rather than learning Fern Ridge while simultaneously managing a major capital program, Scott and the R&C team were able to carry institutional knowledge from facility planning into project development and construction.
The district also maintained strong internal staff continuity throughout the program, helping preserve institutional knowledge and allowing decisions to move efficiently as projects advanced.
From Planning to Performance
With a clear roadmap already established, the district was able to deliberately accelerate the program.
Completing the majority of the work in approximately two years instead of three helped reduce exposure to construction inflation, allowed projects to overlap efficiently and kept contractors and project teams mobilized as work moved between campuses. Early planning also allowed the team to identify procurement and sequencing needs before they became schedule constraints.
The results can be seen across the district.
Elmira High School
Elmira High School received major investments in both academics and athletics. Science classrooms were modernized with updated infrastructure, cabinetry, finishes and safety improvements. Restrooms, parking, driveways and mechanical systems were also improved.
The new athletics complex added an all-weather synthetic turf field, track and field facilities, lighting, grandstands, supporting facilities and expanded opportunities for practices, games and community use. Construction required additional work after challenging soils and drainage conditions were discovered, but the project remained within the adjusted budget.
Fern Ridge Middle School
Educational programming drove the renovation of three science labs, science preparation and safety areas, the Maker Lab, music spaces, special education classrooms, collaborative areas, restrooms and a new staff wellness room.
Construction uncovered drainage and plumbing problems, roofing conditions, additional asbestos and structural reinforcement needs beneath the slab. Despite those discoveries and expanded scope, the project opened on time and finished approximately 20% under budget.
Outdoor improvements also added covered recreation areas, basketball and activity space, improved security fencing and a redesigned bus turnaround that improved campus circulation.
Veneta Elementary School
The Veneta Elementary parking project increased capacity from 58 to 111 spaces, nearly doubling the size of the main lot.
During construction, the team discovered that deteriorating pavement was connected to a larger failure of the underground storm drainage system. Instead of limiting the work to surface repairs, the district replaced the entire main-lot stormwater system and restored its connection to the playground drainage system. The completed project also improved lighting, pedestrian crossings and ADA access.
Veneta Elementary’s gymnasium and student restrooms were also renovated, improving two of the school’s most frequently used spaces. The gym project required additional moisture mitigation within the existing slab, but the issue was resolved without delaying the school opening or exceeding the available project budget.
Elmira Elementary School
Elmira Elementary received new security fencing and an expanded playground environment, creating safer and more engaging outdoor spaces for students.
The playground includes a larger primary play structure along with musical and sensory elements, while the new fencing improved campus security without limiting access to outdoor recreation.
The drainage commitment identified in the bond measure had already been addressed before bond construction began, allowing bond resources to focus on other campus improvements.
Districtwide Mechanical Improvements
Mechanical improvements were completed ahead of schedule and generated approximately 30% savings.
All Fern Ridge schools are now integrated into a districtwide controls system, improving the reliability of heating, ventilation and cooling while giving maintenance staff better tools to monitor and troubleshoot building systems.
Existing equipment was evaluated based on actual condition and need rather than assuming every component required replacement.
Delivering More Than the Original Promise
The district’s first responsibility was to deliver the improvements promised to voters.
Strong program management and savings then created opportunities to address additional needs.
Added work included:
Expanded Elmira High School parking
Replacement of deteriorated EHS courtyard canopies
A new front shelter at Fern Ridge Middle School
A new FRMS staff wellness room
Expanded Veneta Elementary parking
Complete replacement of the VES storm drainage system rather than limited repairs
Districtwide HVAC controls integration
Irrigation improvements across district sites
Development of three additional athletic fields behind Elmira Elementary
Numerous smaller opportunities to repair aging infrastructure, address safety concerns and improve functionality within active work areas
The result is not simply a program that spent less. Fern Ridge protected the original voter commitments and used savings and efficiencies to create additional long-term value.
Project Spotlight: A Championship-Caliber Throws Facility
One of the most distinctive additions to the new Elmira High School athletics complex is its championship-caliber discus and hammer throw facility.
The cage is one of only three facilities of its kind in Oregon, joining facilities at the University of Oregon and Oregon State University.
Local connections also helped increase the value of the investment. David Dumble, former Oregon State University throws coach and owner of Dumble Athletics, and Olympic silver medalist Lance Deal personally participated in the installation, helping eliminate significant shipping and installation expenses.
The facility began attracting outside users during its first summer, including national-level competitors and members of the Swedish National Team training ahead of international competition at Hayward Field.
For Elmira students, the facility provides a high-quality throwing environment and additional opportunities through Junior Olympic and USA Track & Field competition. For the district, it creates new possibilities for camps, outside users and facility rentals.
Keeping the Investment Local
More than 90% of the design and construction firms engaged for the bond program were based in Lane County.
Regional partners included firms such as OEG Electric, Alliant Systems and Delta Sand & Gravel.
That local participation supported responsiveness and continuity throughout the program while keeping a substantial share of the community’s investment within the region.
An Investment That Reaches Every Student
When Scott Rose, Senior Project Manager - R&C Management Group, was asked what he hoped people would remember about the bond program 10 years from now, his answer focused on something larger than any individual project.
Every Fern Ridge student has been positively affected by the investment.
Elementary students gained safer campuses and improved places to play. Middle school students gained stronger science, special education, career exploration and collaborative learning environments. High school students gained modernized learning spaces and expanded athletics opportunities.
Across every school, students and staff benefit from better mechanical systems, improved accessibility, stronger infrastructure and enhanced outdoor spaces.
These improvements also strengthen Fern Ridge as a place where families can see continued investment in their children and their community.
A Community Effort
Fern Ridge Superintendent Gary Carpenter reflected on both the results and the many people behind them in the district’s final community report.
“Every school in our district has seen significant upgrades that will benefit students, staff, families and the greater community for decades to come.”
Carpenter also thanked voters, students, families, current and former Board members, the Facilities Planning Committee, Bond Oversight Committee, design partners, contractors, community members and district staff who contributed to the program.
The Value of Continuity
Fern Ridge’s 2024 Bond Program demonstrates what can happen when facility assessment, long-range planning, educational priorities and project delivery remain connected from the beginning.
R&C is proud to have supported the district across that continuum, from facility assessments and long-range facility planning through owner’s representative services, program management, project management and community communications.
The outcome is more than a completed construction program.
Fern Ridge fulfilled its original bond commitments, accelerated delivery, preserved public resources, expanded the value of the community’s investment and created facilities that will serve students, staff and families for years to come.
About R&C Management Group
R&C Management Group offers comprehensive owner’s representative services including facility assessments, long-range facility planning, program management, project management, budgeting, scheduling, and communications services for public-sector capital programs throughout the Pacific Northwest. R&C works with school districts and other public agencies to connect early planning with successful project delivery and long-term community value.